Project 3 Grading Criteria

  1. Semaphores using semtest1.c,p1.c, p2.c, and p3.c

    At the shell prompt, typing:

     /c/semtest1.exe 
    should output
     
    Semtest1 begins
    p3 created
    Produced 0
    Consumed 0
    Produced 1
    Consumed 1
    Produced 2
    Consumed 2
    Produced 3
    Consumed 3
    Produced 4
    Consumed 4
    p3 executed
    
    Correct implementation of semaphores is worth 30 points.

  2. Semaphore invalid cases using semtest2.c
    semtest2.c
    will check handling of invalid arguments to semaphore operations. At the prompt typing:

     /c/semtest2.exe 
    should output (actual value returned by Init_Semaphore not important).
    + Identified unauthorized call
    + Identified invalid SID
    Open_Semaphore() called
    Open_Semaphore() returned 0
    P() called
    P() returned 0
    V() called
    V() returned 0
    Close_Semaphore() called
    Close_Semaphore() returned 0
    + Removed authority after finish
    
    Correct output gets you 10 points

  3. Scheduling will be tested using ping.c and pong.c.
    At the prompt typing:

    $ /c/ping.exe &
    $ /c/pong.exe 
    
    should output
    Pong
    Ping
    Pong
    Ping
    Pong
    Ping
    Pong
    Ping
    Pong
    Ping
    Process Pong is done at time: YY
    Process Ping is done at time: XX
    
    Note that the last three lines might come out in a different order but that's OK, the important part is the Pong/Ping alternance. Correct output gets you 25 points

    .
  4. Scheduling using schedtest.c,sched1.c, sched2.c, and sched3.c. At the prompt typing:

    /c/schedtest.ex [rr|mys]
    should output a string consisting of many 1s and 2s and a single 3. 3 should never appear as the first character. A sample session is
    %/c/schedtest.ex rr 
    111111222222111111222222311111122222212
    %/c/schedtest.ex mys
    111112222221111113222222111111222222112
    

    A few trials runs will usually (but not certainly) show the 3 appearing earlier when running MYS then when running RR In case of doubt, code will be checked. Correct implementation of scheduling carries 30 points.